Lydia CallowayTrustee, Calloway Family Trust
WorkstreamsSelwyn Court: boiler bidAshdown Lofts: roof codingLinwood Terrace: offers outBellamy Street Flats: 9 of 15

Approvals

The oldest open request, with the rule that holds it and the four ways you can decide when the second bid arrives.

Approval request, updated Oct 1, 2026
A property manager reviewing a repair quote with an owner

Request: Selwyn Court boiler repair

Boiler repair waiting for a second bid Owner limit $1,500 per job Record as of Sep 28, 2026

Every repair above the owner limit goes to the trustee as one request: the quote, the bids, the limit that applies and how long the decision has taken. This request covers the Selwyn Court boiler repair, the oldest open approval at 9 days. Prepared by Luis Navarro, property manager at Moorcroft Property Management, for Lydia Calloway, trustee of the Calloway Family Trust.

Building and area
Selwyn Court, boiler room
Vendor
Brightfield Heating
Quote
$7,800
Bids received
1, and the trust requires 2 above $5,000
Owner limit
Owner approval needed above $1,500 per job
Status
Waiting for bid
Raised
Sep 19, 2026, waiting 9 days on Sep 28
Approver
Lydia Calloway, trustee
Request owner
Luis Navarro, property manager
Priority
Urgent, because heating season starts on Oct 15

The rules that decide the route

The trust sets two thresholds. A job above $1,500 needs the owner's approval before work is booked. A job above $5,000 also needs a second bid, so the owner can compare before deciding. Moorcroft aims to put a complete request in front of Lydia and to record the decision within two days.

Quote for one jobWhat the owner receivesWho decidesTarget
Up to $1,500Nothing to approve. The job is reported in the monthly owner reportProperty managerBooked the same day
Above $1,500 up to $5,000One written quote with the approval requestLydia CallowayDecision within 2 days
Above $5,000The quote and a second written bid, side by sideLydia CallowayDecision within 2 days of the second bid
Urgent or unsafeA temporary repair kept under $1,500, then the full requestProperty manager first, then LydiaTemporary step the same day

How long September decisions took

Seven repairs above the $1,500 limit at the three Calloway buildings needed Lydia's approval in September. The chart groups them by days from request to decision: 1 on the same day, 3 within 1 to 2 days, 1 in 3 to 5 days and 2 in over 5 days.

Four of the seven were decided within two days: Drain camera survey (same day), Apartment turnover flooring (1 day), Elevator door sensor (1 day) and Water heater replacement (2 days). Three waited longer. The two slowest are the Selwyn Court boiler repair and the Ashdown Lofts roof membrane repair.

RequestBuildingQuoteBidsDays to decisionStatus
Boiler repairSelwyn Court$7,80019Waiting for bid
Roof membrane repairAshdown Lofts$12,40026Approved Sep 14
Shop front glazingAshdown Lofts$6,20024Approved Sep 14

The tile below counts the requests decided within two days. It is the measure Moorcroft reports to the trust each month.

Live from the Dashboards appOpen the full report
Live from the Dashboards appOpen the full report

Why the boiler request cannot be approved yet

The other two Calloway requests above $5,000 had both bids in hand when they went to Lydia.

  • Boiler repair: bids in hand, 1 of 2 needed
  • Roof membrane repair: bids in hand, 2 of 2 needed
  • Shop front glazing: bids in hand, 2 of 2 needed

When the second bid arrives, Lydia has four ways to decide. Whichever she picks, the decision date goes into the record, so the days to decision stay accurate.

OptionWhen it fitsWhat happens next
Approve the lower bidBoth bids cover the same workLuis books the vendor and records the decision date
Approve with a conditionThe work needs a start date before Oct 15 or a warranty termLuis confirms the condition with the vendor before booking
Ask for a revised bidThe two bids cover different workLuis requests the revision and the days keep counting
DeclineLydia does not want the repair doneThe temporary repair stays and Luis reports the risk before Oct 15
  1. Request raised for the $7,800 quote, Sep 19
  2. Second bid requested by Luis Navarro
  3. Temporary repair under the owner limit approved by Lydia, Sep 28
  4. Second bid brought to Lydia, before Oct 15
  5. Lydia decides and the decision date is recorded
  6. Permanent repair booked with the approved vendor

"I would rather wait for the second bid than sign a $7,800 repair on one number. Keep the building safe in the meantime and bring me both bids before October 15."

Lydia Calloway, Trustee, Calloway Family Trust

Live from the Dashboards appOpen the full report

Next steps

Open items from the approvals above, with owners

  • Request the second bid for the Selwyn Court boiler repair. Owner: Luis Navarrodone
  • Record Lydia's approval of the temporary repair, Sep 28. Owner: Luis Navarrodone
  • Bring the second boiler bid to Lydia before heating season starts on Oct 15. Owner: Luis Navarroopen
  • Confirm the capital coding of the Ashdown Lofts roof membrane repair with the trust accountant. Owner: Teodor Marinescuopen
  • Schedule the shop front glazing fitting outside shop hours. Owner: Teodor Marinescuopen
  • Confirm the warranty registration for the Apartment 3B water heater at Linwood Terrace. Owner: Luis Navarroopen
  • Book the Apartment 5A flooring fitting before the Oct 10 move-in. Owner: Rashida Okonjoopen
  • Share the basement drain camera survey report with Lydia. Owner: Luis Navarroopen

Prepared and reviewed by

  • Luis NavarroProperty manager, Moorcroft Property Management, prepared this request

  • Sandra IlvesDirector of property operations, Moorcroft Property Management, reviews the limits

  • Lydia CallowayTrustee, Calloway Family Trust, approver